Pembrokeshire County Council has refused expansion plans for a scrap metal and car dismantling facility at Carew Airfield, citing significant noise concerns. The decision blocks the proposed growth of Pembrokeshire Metal Recycling Limited’s operations at Unit C, G Building, Carew Pavilion.
The application, submitted through agent Hayston Developments & Planning Ltd, sought permission to expand the existing scrap metal storage and metal recycling facility. Works at the site reportedly began last October, prompting the retrospective planning application to regularise the development.
Carew Community Council formally objected to the proposal, raising concerns regarding potential groundwater pollution. They also highlighted issues related to noise, visual impact, and the attraction of vermin to the expanded operational area.
A supporting statement noted that planning permission was previously granted in 2022 for a change of use from scrap metal storage to a metal recycling and vehicle dismantling facility. The site had previously operated as a scrap metal yard, gradually expanding into additional land over the years.
The applicant received details of an enforcement notice last June, alleging that a breach of planning control had occurred on the land. This led to an appeal for an extension of time for compliance, as outlined in the official documentation.
The statement added: “This planning practice has been engaged to resolve the planning issues associated with the operation of the site and the Enforcement Notice and to find a planning solution for the site.”
It further stated: “Hence, this retrospective planning application.” It said the scheme ‘can be acceptable for this site and location, as it would represent a logical extension to an existing lawful use.
The applicant believed that any visual and potential environmental impacts could be sufficiently mitigated and controlled through the proposed conditions. They argued the expansion was a necessary step to resolve ongoing planning irregularities at the facility.
An officer report recommending refusal described the scheme as essentially seeking to regularise the ‘creep’ of the existing scrap yard into the neighbouring plot. The report clarified that no new processes or operations were proposed for the extension area.
The use of the ‘extension’ site would be for storage of scrap from the adjacent site, overflow car parking, and relocation of offices. The report noted that the development would not pose an unacceptable risk to aquifer quality, provided NRW conditions were met.
However, concerns were raised following numerous responses relating to noise from the existing site. The report highlighted the “potential for unacceptable noise levels that would arise which would have a significant detrimental impact on local amenity.”
The application was refused on the grounds it “would substantially increase the operational area available to the existing metal recycling and vehicle dismantling facility.” This would facilitate a wider spatial distribution of operations and associated noise-generating activities across the site.
Evidence obtained by the Council’s Pollution Control Team demonstrated that existing operations already give rise to noise levels resulting in a significant adverse impact at nearby noise-sensitive receptors. The additional operational area would facilitate activities capable of exacerbating these existing noise impacts, to the detriment of the amenity of nearby occupiers.